Elcro Digital Services, LLC. - Fremont BGP ASN Migration – Maintenance details

All systems operational

Fremont BGP ASN Migration

Completed
Scheduled for June 01, 2025 at 9:00 AM – 9:52 AM

Affects

Data Centers

Under maintenance from 9:00 AM to 9:52 AM

FMT1 - Fremont, CA

Under maintenance from 9:00 AM to 9:52 AM

Internal Systems

Under maintenance from 9:00 AM to 9:52 AM

Virtual Private Servers

Under maintenance from 9:00 AM to 9:52 AM

Updates
  • Completed
    June 01, 2025 at 9:52 AM
    Completed
    June 01, 2025 at 9:52 AM
    Maintenance has completed successfully.
  • In progress
    June 01, 2025 at 9:00 AM
    In progress
    June 01, 2025 at 9:00 AM
    Maintenance is now in progress
  • Planned
    June 01, 2025 at 9:00 AM
    Planned
    June 01, 2025 at 9:00 AM

    This is a rescheduling announcement for the postponed maintenance for Fremont, CA.

    We will be performing scheduled network maintenance in our Fremont data center to migrate BGP routing to Elcro's ASN. This includes switching our /24 IP block and all BGP sessions in that location.

    Only network services will be affected - servers will remain online but may be unreachable during routing changes.

    The duration is blocked for 2 hours but is expected to be much shorter. We appreciate your patience during this switchover as we work to improve our network performance and reliability.